Work has now been postponed on the Maggie project due to Covid 19, however the latest information is:

Due to site levels, the number of stores has reduced to 5x single units to fit the site constraints, but this will have no impact on available units to let to fishermen. There will be 3x lettable units and 1x garage for the fishermens' forklift. The final unit will be for Harbourmaster use.

Work had started on-site with AG Thomson working on the foundations and slab. A concrete access ramp will eventually follow when possible and then the timber kit.

Photo by Kenny Maule