With licences now in place, the RNLI hope to make best use of the low spring tides at the end of February and March, having taken careful note of Craning-In Day and the North Wall Repair project.

The contractor’s compound should be near the bridge approach and an additional area in front of the RNLI station.

The bridge-lift will be coordinated with the harbour master and care will be taken that no temporary works should be placed which would prevent boats going under the bridge near high tide.

Click READ MORE button to see the survey team measuring during last year's planning.